Schedule Development

Schedule Development

To Complete Performance Index

The To Complete Performance Index (TCPI) is a comparative Earn Value Management (EVM) metric used primarily to determine if an independent estimate at completion is reasonable. It computes the future required cost efficiency needed to achieve a target Estimate at Completion (EAC). TCPI Definition: It is a measure of the cost performance that is required […]

Schedule Development

To Complete Performance Index Read More »

Schedule Development

'What if' scenario analysis

‘What if’ scenario analysis is a simulation method that compares and measures the effects of different scenarios on a project schedule. It uses Schedule Network Analysis to determine the effects of various scenarios on a project schedule from delayed activities, strikes, bad weather, late resources, and other adverse situations. This analysis is used to plan

Schedule Development

'What if' scenario analysis Read More »

Schedule Development

Schedule Control

Step 5: Schedule Control in the Schedule Preparation process is to identify schedule variations and to manage actual changes to the developed schedules. (see Controlling Process) A schedule change control system that defines the procedures by which changes can be made should be established and integrated into the program’s overall change control system. The schedule

Schedule Development

Schedule Control Read More »

Schedule Development

Schedule Compression

Schedule compression, also known as time compression or schedule crashing, is a technique used in project management to shorten an already-developed schedule. This might be done to meet an updated delivery date, a new opportunity, or a schedule delay. It’s done without changing the scope of the program. Definition: Schedule compression is a project management

Schedule Development

Schedule Compression Read More »

Schedule Development

Schedule Development

Step 4: Schedule Development involves the development of realistic start and finish dates for each activity. An iterative process, schedule development takes into account activity sequencing, duration estimates, resource requirements and availability, calendars that show when work can be performed, constraints, assumptions, and risk. [1] The output of this step is a set of schedules

Schedule Development

Schedule Development Read More »

Schedule Development

Resource Leveling

Resource leveling is a scheduling technique that addresses the availability of resources, usually manpower and equipment. Project personnel will modify scheduled activities to accommodate resource availability or unavailability. If resources are available only in limited quantities, they will change the timing of activities so that the most critical activities have enough resources to be completed,

Schedule Development

Resource Leveling Read More »

Schedule Development

Integrated Master Schedule (IMS)

The Integrated Master Schedule (IMS) is a time-based schedule containing the networked, detailed tasks necessary to ensure successful program/contract execution. The IMS is traceable to the Integrated Master Plan (IMP), Work Breakdown Structure (WBS), Statement of Work (SOW), Contractor Performance Report (CPR), and Earn Value Management system (EVMS). Definition: The Integrated Master Schedule (IMS) is

Schedule Development

Integrated Master Schedule (IMS) Read More »

Schedule Development

Precedence Diagram Method (PDM)

Precedence Diagram Method (PDM) is a visual representation technique that depicts the activities involved in a project. It is a method of constructing a project schedule network diagram that uses boxes/nodes to represent activities and connects them with arrows that show the dependencies. It’s also sometimes called the activity-on-node (AON) method. Purpose of Precedence Diagram

Schedule Development

Precedence Diagram Method (PDM) Read More »

Schedule Development

Line of Balance (LOB)

Line of Balance (LOB) is a management control process for collecting, measuring, and presenting facts relating to time (see Schedule Control), cost, and accomplishment – all measured against a specific plan. It shows the process, status, background, timing, and phasing of the project activities, thus providing management with measuring tools that help: Comparing actual progress

Schedule Development

Line of Balance (LOB) Read More »

Schedule Development

Activity Sequencing

Step 2: Activity Sequencing involves the accurate identification of constraints/relationships among activities and establishing the order in which the activities will be accomplished. There are several inputs to this step: [1] The activity list developed in the Activity Definition step, The product description and characteristics, Mandatory constraints/dependencies, such as the fact that a prototype must

Schedule Development

Activity Sequencing Read More »

Schedule Development

Critical Chain Method

The Critical Chain Method (CCM) is used to perform Schedule Network Analysis that considers task dependencies, limited resource availability, and buffers.  It’s used to prepare the project schedule when limited or restricted resources are available. In this method, the Program Manager (PM) usually schedules all or most high-risk or critical activities in the earlier stage of

Schedule Development

Critical Chain Method Read More »

Schedule Development

Scheduling Guide for Program Managers

  The Defense System Management College Scheduling Guide for Program Managers, dated Oct 2001, is an introduction to scheduling. It is meant for people who already have some experience in program management and those who seek to learn more about the subject. It is not a detailed treatment of the subject, but instead, explains how

Schedule Development

Scheduling Guide for Program Managers Read More »

Schedule Development

Program Evaluation and Review Technique (PERT) Analysis

Program Evaluation and Review Technique (PERT) is a method used to examine the tasks in a schedule and determine a Critical Path Method variation (CPM). It analyzes the time required to complete each task and its associated dependencies to determine the minimum time to complete a project. It estimates the shortest possible time each activity will

Schedule Development

Program Evaluation and Review Technique (PERT) Analysis Read More »

Schedule Development

Critical Path Length Index (CPLI)

The Critical Path Length Index (CPLI) is a metric used to measure the relative efficiency to complete a milestone on time. It’s used to calculate and graphically display the Critical Path; the longest series of scheduled activities to complete a project. CPLI is a OSD(A&S) tripwire metric. CPLI = (Critical Path Length +/- Total Float

Schedule Development

Critical Path Length Index (CPLI) Read More »