Schedule Development

Schedule Development

Schedule Risk

Schedule risk is the likelihood of failing to meet schedule plans and the effect of that failure. It exists in every schedule and is impossible to predict, with complete confidence, the length of time necessary to complete an activity, meet a milestone, or deliver a system. Little information exists in the early phases of a …

Schedule Development

Schedule Risk Read More »

Schedule Development

Schedule Control

Step 5: Schedule Control in the Schedule Preparation process is to identify schedule variations and to manage actual changes to the developed schedules. (see Controlling Process) A schedule change control system that defines the procedures by which changes can be made should be established and integrated into the program’s overall change control system. The schedule …

Schedule Development

Schedule Control Read More »

Schedule Development

Schedule Development

Step 4: Schedule Development involves the development of realistic start and finish dates for each activity. An iterative process, schedule development takes into account activity sequencing, duration estimates, resource requirements and availability, calendars that show when work can be performed, constraints, assumptions, and risk. [1] The output of this step is a set of schedules …

Schedule Development

Schedule Development Read More »

Schedule Development

Network Diagram

Network Diagrams are a graphical portrayal of the activities and events of a project. They show how each activity relates to others in the project, the sequence of activities, and the need to perform some tasks before others. Networks also facilitate the determination of the impact of early or late starts or finishes, provide information about …

Schedule Development

Network Diagram Read More »

Schedule Development

Resource Leveling

Resource leveling is a scheduling technique that addresses the availability of resources, usually manpower and equipment. Project personnel will modify scheduled activities to accommodate resource availability or unavailability. If resources are available only in limited quantities, they will change the timing of activities so that the most critical activities have enough resources to be completed, …

Schedule Development

Resource Leveling Read More »

Schedule Development

Integrated Master Schedule (IMS)

The Integrated Master Schedule (IMS) is a time-based schedule containing the networked, detailed tasks necessary to ensure successful program/contract execution. The IMS is traceable to the Integrated Master Plan (IMP), Work Breakdown Structure (WBS), Statement of Work (SOW), Contractor Performance Report (CPR), and Earn Value Management system (EVMS). Definition: The Integrated Master Schedule (IMS) is …

Schedule Development

Integrated Master Schedule (IMS) Read More »