| MDD | MS A | RFP | MS B | MS C | FRP |
| Acquisition Decision Memorandum (ADM) | R | R | | R | R | R |
| 2366a Written Determination | | S | | | | |
| 2366b Certification and Determination | | | | S | S | |
| Acquisition Program Baseline (APB) | | | R | S | S | S |
| Acquisition Strategy | | R | R | R | R | R |
| Acquisition Information Assurance Strategy | | X | | X | | |
| Affordability Analysis | R | R | R | R | R | R |
| Alternative Live-Fire Test and Evaluation Plan or Waiver | | | | | | |
| Analysis of Alternatives (AoA) | | S | R | | R | |
| Analysis of Alternatives (AoA) Study Guidance | R | | | | | |
| Bandwidth Requirements Review (BRR) | | | S | S | S | |
| Benefit Analysis and Determination | | S | S | | S | |
| Beyond Low Rate Initial Production (LRIP) Report | | | | | | |
| Business Process Re-engineering | S | S | S | S | S | |
| Capability Development Document (CDD) | | R | R | | R | |
| Capability Production Document (CPD) | | | | | R | |
| Clinger-Cohen Act (CCA) Compliance | | S | | S | S | S |
| Competitive Analysis | | | | | | |
| Concept of Operations (CONOPS) | | R | | R | R | |
| Contract Type Determination | | | S | S | S | |
| Core Logistic/Source of Repair Analysis | | | | X | X | |
| Corrosion Prevention Control Plan | | | | R | R | |
| Cost Analysis Requirements Description (CARD) | | R | R | R | R | R |
| Cybersecurity Strategy | | S | S | S | S | S |
| Data Management Strategy | | X | | X | X | X |
| Develop RFP Release Cost Estimate | | | R | | | |
| DoD Component Cost Estimate | | R | | R | R | R |
| DoD Component Cost Position | | R | | R | R | R |
| DOT&E Report on Initial Test and Evaluation (IOT&E) | | | | | | S |
| Economic Analysis | | X | | X | X | X |
| Exit Criteria | | R | R | R | R | |
| Frequency Allocation Application (DD Form 1494) | | S | | S | S | |
| Full Funding Certification Memorandum | | R | | R | R | R |
| General Equipment Validation | | | | | S | S |
| Industrial Base Capabilities Consideration | | S | S | | S | |
| Independent Cost Estimate (ICE) | | S | | S | S | S |
| Independent Logistics Assessment | | | | S | S | S |
| Independent Technology Readiness Assessment | | | | X | X | |
| Information Support Plan (ISP) | | | R | | R | |
| Information Technology and National Security Interoperability Certification | | | | | | R |
| Initial Capabilities Document (ICD) | R | | | | | |
| Initial Operational Test and Evaluation (IOT&E) Completed | | | | | | X |
| Intellectual Property (IP) Strategy | | S | S | S | S | S |
| Item Unique Identification (IUID) Implementation Plan | | R | R | R | R | |
| Joint Interoperability Test Certification | | | | | | X |
| Life-Cycle Mission Data Plan (LMDP) | | R | R | R | R | R |
| Life-Cycle Sustainment Plan (LCSP) | | R | R | R | R | R |
| Live-Fire Test and Evaluation Plan, Report, Waiver | | | | X | X | S |
| Low-Rate Initial Production (LRIP) Quantity | | | S | S | | |
| Market Research | S | S | S | | | |
| Net-Centric Data & Service Strategy | | X | | X | X | |
| Operational Test Agency (OTA) Report on OT&E activity | | | | | | R |
| Peliminary Design Review (PDR) Report | | | | X | | |
| PESHE and NEPA/E.O. 12114 Compliance Schedule | | | | S | S | S |
| Post Implementation Review | | | | | | X |
| Program Protection Plan (PPP) | | R | R | R | R | R |
| Program Environment, Safety, & Occup Health Evaluation (PESHE) | | | | X | X | X |
| Replaced System Sustainment Plan | | S | | S | | |
| Selected Acquisition Report (SAR) | | | | X | | |
| Should-Cost Target | | R | R | R | R | R |
| Small Business Innovation Research (SBIR) | | S | S | S | S | S |
| Small Business Technology Transfer (STTR) Program | | S | S | S | S | S |
| Spectrum Supportability Risk Assessment/Determination | | R | | R | R | |
| Systems Engineering Plan (SEP) | | R | R | R | R | |
| Technical Data Rights Strategy | | X | | X | X | X |
| Technology Development Strategy (TDS) | | | | | | |
| Technology Readiness Assessment (TRA) | | | S | S | S | |
| Technology Targeting Risk Assessment | | R | | | | |
| Termination Liability Estimate | | S | S | | S | S |
| Test and Evaluation Master Plan (TEMP) | | R | R | R | R | R |
| Test & Evaluation Strategy (TES) | | X | | | | |
| Validated On-line Life-cycle Threat (VOLT) | R | | | | | |