Milestone Matrix

The Defense Acquisition System divides acquisition programs into four (4) Acquisition Categories (ACAT): ACAT 1, ACAT 1A, ACAT 2 or ACAT 3. The table below lists the mandatory deliverables (Regulatory & Statutory) at certain milestones for each ACAT type.

ACAT 1C or 1D

MDD MS A  RFP MS B MS C FRP
Acquisition Decision Memorandum (ADM) R R   R R R
2366a Written Determination          
2366b Certification and Determination        
Acquisition Program Baseline (APB)     R S S S
Acquisition Strategy   R R R R
Acquisition Information Assurance Strategy   X      
Affordability Analysis R R R R
Alternative Live-Fire Test and Evaluation Plan or Waiver          
Analysis of Alternatives (AoA)   S R   R  
Analysis of Alternatives (AoA) Study Guidance R          
Bandwidth Requirements Review (BRR)      S  
Benefit Analysis and Determination    S    
Beyond Low Rate Initial Production (LRIP) Report            
Business Process Re-engineering  S  S  
Capability Development Document (CDD)   R R    
Capability Production Document (CPD)         R  
Clinger-Cohen Act (CCA) Compliance   S   S S S
Competitive Analysis            
Concept of Operations (CONOPS)    R    R  
Contract Type Determination      S  
Core Logistic/Source of Repair Analysis       X X  
Corrosion Prevention Control Plan       R R  
Cost Analysis Requirements Description (CARD)   R R R R
Cybersecurity Strategy   S S
Data Management Strategy   X   X X X
Develop RFP Release Cost Estimate      R      
DoD Component Cost Estimate   R  
DoD Component Cost Position    
DOT&E Report on Initial Test and Evaluation (IOT&E)          
Economic Analysis   X   X X X
Exit Criteria   R R R  
Frequency Allocation Application (DD Form 1494)    S    
Full Funding Certification Memorandum     R
General Equipment Validation          S
Industrial Base Capabilities Consideration    S  S   S  
Independent Cost Estimate (ICE)   S   S S
Independent Logistics Assessment        S
Independent Technology Readiness Assessment       X X  
Information Support Plan (ISP)      R   R  
Information Technology and National Security Interoperability Certification          
Initial Capabilities Document (ICD) R          
Initial Operational Test and Evaluation (IOT&E) Completed           X
Intellectual Property (IP) Strategy    S S
Item Unique Identification (IUID) Implementation Plan   R  R R R  
Joint Interoperability Test Certification           X
Life-Cycle Mission Data Plan (LMDP)   R R R R 
Life-Cycle Sustainment Plan (LCSP)   R R R R
Live-Fire Test and Evaluation Plan, Report, Waiver       X X S
Low-Rate Initial Production (LRIP) Quantity     S    
Market Research S S      
Net-Centric Data & Service Strategy   X   X X  
Operational Test Agency (OTA) Report on OT&E activity           R
Peliminary Design Review (PDR) Report       X    
PESHE and NEPA/E.O. 12114 Compliance Schedule       S
Post Implementation Review           X
Program Protection Plan (PPP)   R R R R 
Program Environment, Safety, & Occup Health Evaluation (PESHE)       X X X
Replaced System Sustainment Plan        
Selected Acquisition Report (SAR)       X    
Should-Cost Target   R R R  R
Small Business Innovation Research (SBIR)   S
Small Business Technology Transfer (STTR) Program   S
Spectrum Supportability Risk Assessment/Determination     R R  
Systems Engineering Plan (SEP)   R  R R R  
Technical Data Rights Strategy   X   X X X
Technology Development Strategy (TDS)            
Technology Readiness Assessment (TRA)     S S S  
Technology Targeting Risk Assessment   R         
Termination Liability Estimate    S S  
Test and Evaluation Master Plan (TEMP)    R R R R
Test & Evaluation Strategy (TES)   X        
Validated On-line Life-cycle Threat (VOLT)          