Major Reviews

Preliminary Design Review (PDR)

The Preliminary Design Review (PDR) is a technical assessment that establishes the Allocated Baseline of a system to ensure a system is operationally effective.  A PDR is conducted before the start of detailed design work and is the first opportunity for the Government to observe the Contractor’s hardware and software design closely.  This review assesses the allocated design documented in subsystem product specifications for each configuration item in the system. It ensures that each function in the Functional Baseline has been allocated to one or more system configuration items. A PDR is required by statute for all Major Defense Acquisition Programs (MDAPs)

Definition: The Preliminary Design Review (PDR) is a review conducted to evaluate the progress, technical adequacy, and risk resolution of the selected design approach for one or more configuration items; to determine each design’s compatibility with the requirements for the configuration item; to evaluate the degree of definition and assess the technical risk associated with the selected manufacturing methods and processes; to establish the existence and compatibility of the physical and functional interfaces among the configuration items and other items of equipment, facilities, software and personnel; and, as applicable, to evaluate the preliminary operational and support documents. – ISO/IEC/IEEE. 2009. Systems and Software Engineering – System and Software Engineering Vocabulary (SEVocab).

Purpose of the Preliminary Design Review (PDR)

The PDR establishes the allocated baseline (hardware, software, human/support systems) and underlying architectures to ensure that the system under review has a reasonable expectation of satisfying the requirements within the currently allocated budget and schedule.

Acquisition System

Fact Sheet: Preliminary Design Review (PDR) Fact Sheet

When to Conduct a Preliminary Design Review (PDR) [1]

A Preliminary Design Review (PDR) should be conducted when the Program Manager believes the system is ready for the following.

  • The PDR is performed during the Technology Maturation & Risk Reduction (TMRR) Phase before Milestone B, when the System Developer has initially baselined the high-level system architectural design.
  • The PDR should be conducted when the allocated baseline has been achieved, allowing the detailed design of hardware and software CIs to proceed. A rule of thumb is that 10 to 25 percent of product drawings and associated instructions should be complete and that 100 percent of all safety‐critical component (Critical Safety Items and Critical Application Items) drawings are complete.
  • The PDR should be conducted when all major design issues have been resolved, and work can begin on detailed design. The PDR should address and resolve critical, system‐wide issues before detailed design begins. [1]
  • A PDR may be conducted incrementally for complex systems for each configuration item. These incremental reviews lead to an overall system-level PDR. System-level performance is supported by compliance with Interface Control Documents but is not assured. Interface requirements make up each configuration item Allocated Specification.

Mandatory Preliminary Design Review (PDR)

For Major Defense Acquisition Programs (MDAP) programs, a PDR assessment is conducted and provided to the Milestone Decision Authority (MDA). DASD(SE) conducts a PDR assessment for ACAT ID programs to inform the MDA of technical risks and the program’s readiness to proceed with detailed design. For ACAT IC programs, the Component Acquisition Executive conducts the PDR assessment.  The timing of the review should consider the following:

  • Unless excused, PDR is carried out for all programs before Milestone B and before the contract award for engineering and manufacturing development. The Milestone Decision Authority (MDA) is also required under 10 U.S.C. 2366b to certify all Major Defense Acquisition Programs (MDAPs) at Milestone B. A PDR must be conducted and evaluated for this certification unless it is waived for grounds of national security.
  • The timing of PDR in relation to the Development Request for Proposal (RFP) Release Decision Point is at the discretion of the DoD Component. It should balance the expense of extending the activities of multiple sources or having a development gap with the necessity for more mature design information. Regardless of this connection, the PDR assessment is carried out before Milestone B to help the MDA choose to start the detailed design phase.

Successful Completion of the PDR

A successful PDR is predicated on determining that the subsystem requirements, preliminary subsystem design, results of peer reviews, and plans for development, testing, and evaluation form a satisfactory basis for proceeding into detailed design and test procedure development. A PDR should produce the following. [1]

Preliminary Design Review (PDR)  Completed Allocated Baseline

The allocated baseline (Configuration Baseline) is the configuration items making up a system and how system function and performance requirements are allocated across lower-level configuration items (hence the term allocated baseline). The PDR defines the allocated baseline and is formally under configuration control and is finished when the following conditions are met.

  • All system-level functional and interface requirements have been decomposed and allocated to the lowest level of the specification tree for all system elements.
  • All external interfaces to the system, as addressed in the System Requirements Review, have been documented in interface control documents.
  • All internal interfaces of the system (system element to system element) have been documented in interface control documents.
  • Verification requirements to demonstrate achievement of all specified allocated performance characteristics have been documented.
  • Design constraints have been captured and incorporated into the requirements and design.

Preliminary Design Review (PDR) Roles and Responsibilities

When thinking about the roles and responsibilities of the Program Manager (PM) and Systems Engineer, the following tasks and roles should be taken into account when conducting a PDR:

The following are some of the Program Manager’s duties:

  • Approve, pay, and hire people for the system PDR as planned in the Systems Engineer Plan (SEP).
  • Setting up the plan to CDR in the SE Management Plan (SEMP), Integrated Master Schedule (IMS), and Integrated Master Plan (IMP), which are all part of the deal.
  • Make sure that the SEP includes experts in the field in each study.
  • Control the configuration of the subset of the functional and assigned baselines the government controls. Hold Configuration Steering Board meetings when changes are needed.

The following are some of the things the Systems Engineer is responsible for:

  • Creating and carrying out system PDR plans with clear, measurable review criteria carefully designed to meet program goals.
  • Making sure that the PDR standards that have already been set have been met.
  • Giving the industry a chance to participate in this PDR planning (where possible, pre-contract award is a best practice).
  • Making sure that assessments and risks related to all design constraints and considerations (like reliability and maintainability, corrosion, and Environment, Safety, and Occupational Health (ESOH) factors) are done, written down, and given.
  • Plans for risk, issue, and chance are being updated. Identifying, mitigating, and monitoring risks and problems; and identifying, analyzing, managing, and tracking opportunities.

Preliminary Design Review (PDR) Benefits

Conducting a PDR offers many benefits crucial to the successful development and management of Major Defense Acquisition Programs (MDAPs).

  • The PDR is a pivotal step in establishing the technical basis for the Cost Analysis Requirements Description (CARD). By meticulously documenting assumptions and rationale, it provides a comprehensive foundation for an accurate cost estimate for the Acquisition Program Baseline (APB). This, in turn, facilitates technically informed cost estimates, enabling more effective should-cost/will-cost management throughout the project’s lifecycle.
  • The PDR helps define the technical requirements essential for the detailed design phase, EMD (Engineering and Manufacturing Development) contract specifications, and the Statement of Work (SOW).
  • The review process establishes a robust basis for quantifying risks and identifying opportunities, contributing to informed decision-making and risk mitigation strategies.
  • The technical foundation laid during the PDR is instrumental in meeting the 10 USC 2366b certification requirements, a mandatory step for all MDAPs, ensuring adherence to regulatory standards, and bolstering the overall success of the program.

The Weapons System Acquisition Reform Act of 2009 directed the PDR to:

  • PDRs before Milestone (MS) B is mandatory for all Major Defense Acquisition Programs (MDAP) and will be reflected in the Technology Development Strategy (TDS) to be approved by the MDA at MS A. Post-PDR assessments will be conducted in association with MS B preparations and will be formally considered by the Milestone Decision Authority (MDA) at the MS B certification review.
  • The timing of PDRs for other than MDAPs will be approved by the DoD Component MDA when consistent with TDS or Acquisition Strategy objectives. When the PDR is conducted before MS B, a post-PDR assessment will be conducted in association with the MS B review and formally considered by the MDA at the MS B review. If the PDR is conducted after MS B, the MDA will conduct a post-PDR assessment at a time reflected in the approved acquisition strategy.
  • PDR before MS B is now a statutory requirement for MDAPs. The post-PDR assessment will be conducted during the MS B review and prior to the section 2366b certification by the MDA per title 10, Unites States Code.

Difference Between Preliminary Design Review (PDR) and Critical Design (CDR) Review

A Preliminary Design Review (PDR) is conducted to ensure new technologies are mature enough to be integrated into a product subsystem to form its allocated baseline and is required by statute for all Major Defense Acquisition Programs (MDAPs). A Critical Design Review (CDR) determines if a system can meet its stated performance requirements within cost, schedule, and risk. It’s an independent assessment that informs the Milestone Decision Authority (MDA) of the technical risks and the program’s readiness to proceed with fabrication, system integration, demonstration, and test.

AcqNotes Tutorial

AcqTips:

  • The Program Manager (PM) should conduct the PDR when all major design issues have been resolved, and work can begin on the detailed design. The PDR should address and resolve critical, system-wide issues.
  • IEEE 5288.2 “Standard for Technical Reviews and Audits on Defense Programs” is the standard for technical reviews and audits to be performed throughout the acquisition life cycle for the US Department of Defense (DoD) and other defense agencies. This standard guides the DoD and contractor on what is required during an SRR
  • The PDR should be conducted when the allocated baseline has been achieved, allowing the detailed design of hardware and software configuration items to proceed. A rule of thumb is that 10 percent to 25 percent of product drawings and associated instructions should be complete and that 100 percent of all safety-critical component (Critical Safety Items and Critical Application Items) drawings are complete.

AcqLinks and References:

Updated: 2/5/2024

Rank: G3.5

Leave a Reply