A Pre-award Survey (FAR 9.106) is an evaluation by a surveying activity of a Prospective Contractor’s Capability to perform under the terms of a proposed contract. It typically requires an on-site visit to the prospective contractor’s facility. Due to the length and expense, pre-award surveys are not typically performed for contracts that are less than the simplified acquisition threshold of $100,000.
Website: FAR 9.106 “Pre-award Survey”
Form 1403: Pre-award Survey of Prospective Contractor
Purpose of Pre-Award Survey
The purpose of a Pre-Award Survey is to determine if a prospective awardee contractor is responsible and has the ability to perform to the requirements of the contract.
Pre-Award Survey Insufficient Information
When the Procuring Contracting Officer (PCO) from the buying activity has insufficient information to determine if a prospective contractor is responsible, he or she completes a request for a Pre-award Survey (PAS). The PCO identifies on the PAS Standard Form 1403:
- The factors that need to be evaluated in the survey
- Any personnel from the contracting officer who will participate in the survey
- The complete solicitation package (unless it has previously been furnished), and any information indicating prior unsatisfactory performance by the prospective contractor;
- The due date for reporting the results of the Pre-award Survey
Pre-Award Missing Factors
The PCO must have sufficient information on all factors. The information requested depends on what is missing. The level of detail requested depends on the complexity and dollar value of the item being procured. The five (5) evaluation factors that may be considered on the SF 1403 are:
- Technical capability (SF 1404)
- Production capability (SF 1405)
- Quality assurance (SF 1406)
- Financial capability (SF 1407)
- Accounting system (SF 1408)
AcqLinks and References:
Updated: 7/20/2021
Rank: G1